Question: Question: A project precedence table with normal and crash times and cost is given in tables: Question: A project precedence table with normal and crash

Question: A project precedence table with normal and crash times and cost is given in tables:

Question: A project precedence table with normal and crash times and cost

Question: A project precedence table with normal and crash times and cost is given in tables: Activity Predecessor Normal Time Crash Times Normal Crash (Weeks) (Weeks) Cost Cost (RS.) (RS) A - 4 2 8000 9000 B A 5 2 16000 20000 C A 4 1 12000 13000 D B,C 6 4 34000 35000 E A 6 4 42000 44000 E 5 3 16000 16500 G D,F 7 4 66000 72000 H G,D 4 2 2000 5000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!