Question: Question: A project precedence table with normal and crash times and cost is given in tables: Question: A project precedence table with normal and crash
Question: A project precedence table with normal and crash times and cost is given in tables:

Question: A project precedence table with normal and crash times and cost is given in tables: Activity Predecessor Normal Time Crash Times Normal Crash (Weeks) (Weeks) Cost Cost (RS.) (RS) A - 4 2 8000 9000 B A 5 2 16000 20000 C A 4 1 12000 13000 D B,C 6 4 34000 35000 E A 6 4 42000 44000 E 5 3 16000 16500 G D,F 7 4 66000 72000 H G,D 4 2 2000 5000
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
