Question: (Question C). Three alternatives are being considered. Alternative A has a useful life of 3 years. Alternative B. is 5 years, Alternative C. is 6

 (Question C). Three alternatives are being considered. Alternative A has a

(Question C). Three alternatives are being considered. Alternative A has a useful life of 3 years. Alternative B. is 5 years, Alternative C. is 6 years. Using the least common multiple approach what is the planning horizon? (a). 6 years (b). 14 years (c). 18 years (d).30 years