Question: Question Completion Status: 1) A Moving to the next question prevents changes to this answer. Question 6 Mor Task Task Time Task Predecessors seconds A
Question Completion Status: 1) A Moving to the next question prevents changes to this answer. Question 6 Mor Task Task Time Task Predecessors seconds A 140 B 120 JA 240 D 120 E 1480 CD F 400 A G 380 EF Answer the questions based on a 50 demand per day and an 7 hours of working hours Minimum number of work stations- 2 Minimum number of work stations- 3 O Minimum number of work station 4 Minimum number of work stations= 5 18 Er // . w 38C juos