Question: Question Completion Status: 7 10 13 n A Moving to another question will save this response. Question 33 Cost (SR) 00014 Activity Description of work
Question Completion Status: 7 10 13 n A Moving to another question will save this response. Question 33 Cost (SR) 00014 Activity Description of work Preceding Activity Time Activity (days) A Excavation NIL 5 B Foundation A 6 Concrete B 8 D Roofing 6 E Electrical D 4 F Plumbing & Sanitation E 4 G Floor & Wall finishes C 10 H Painting 9 Cleaning & Handover G 6 20000 30000 25000 12000 10000 8000 9000 6000 5000 Based on the table above. Develop a Gantt Chart and answer the following question How many days will it take to complete this project? O 39 days 33 days O 37 days 35 days