Question: Question Completion Status: A . Moving to the next question prevents changes to this answer. Question 1 4 The client demands changes to the product
Question Completion Status:
A Moving to the next question prevents changes to this answer.
Question
The client demands changes to the product specification that will add only two weeks to the critical path. Which of the following is the best thing for the project manager to do Compress the schedule to recover the tyo weeks.
Cut scope to recover the two weeks.
Crash your project.
Advise the client of the impact of the change.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
