Question: Question Completion Status: A network of a PERT problem consists of the following list. Times are given in weeks. table [ [ Activity ,

Question Completion Status:
A network of a PERT problem consists of the following list. Times are given in weeks.
\table[[Activity,Preceding,Optimistic,Most Likely,Pessimistic],[A,-,5,11,14],[B,-,3,3,9],[C,-,7,9,11],[D,A, B,3,5,7],[E,B,4,6,11],[F,C,6,8,13],[G,D, E,2,4,6],[H,F,3,3,9]]
I. If the activities in the critical path are C,F, and H . Find the expected completion time of the entire duration of the project. The lettelr associated with the correct answer is
a)12.5 weeks
b)17.5 weeks
c)21.5 weeks
d)26.5 weeks
e) None of the above
II. If the activities in the critical path are C,F, and H . Find the standard deviation of the of the entire duration of the project. The letter associated with the correct answer is
a)1.36
b)1.67
c)2.13
d)2.80
e) None of the above
III. Find the duration time of the project that provides a 80% chance of on-time completion. The letter associated with the correct answer is
a)22.23 weeks
b)22.90 weeks
Click Save and Submit to save and submit. Click Save All Answers to save all answers.
a)12.5 weeks
b)17.5 weeks
c)21.5 weeks
d)26.5 weeks
e) None of the above
II. If the activities in the critical path are C, F, and H. Find the standard deviation of the of the entire duration of the project. The letter associated with the correc answer is
a)1.36
b)1.67
c)2.13
d)2.80
e) None of the above
III. Find the duration time of the project that provides a 80% chance of on-time completion. The letter associated with the correct answer is
a)22.23 weeks
b)22.90 weeks
c)23.85 weeks
d)24.64 weeks
e) None of the above
Click Save and Submit to save and submit. Click Save All Answers to save all answers.
Question Completion Status: A network of a PERT

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!