Question: Question completion status: Activity Normal Duration ( hours ) Crash Duration ( hours ) Normal Cost ( $ ) Crash Cost ( S ) Immediate

Question completion status:
Activity
Normal
Duration (hours)
Crash
Duration (hours)
Normal
Cost ($)
Crash
Cost (S)
Immediate
Predecessors
A
2
2
10
-
None
B
3
2
15
23
C
4
25
30
B
3
1
20
24
E
6
4
30
45
1
5
C,E
7
6
35
50
F
10
7
50
62
D,G
Please answer the following questions. (hint, the latest finish of Activity E is 16).
1. The Project completion time is 34
hours.
2. For Activity B, the Earliest Start is 2
3. For Activity C, the Latest Start is 5
4. For Activity E, the Earliest Start is 10
5. For Activity G, the Latest Start is 17
6. For Activity H, the Earliest Start is 24
, the Earliest Fir
, the Latest Finisi
, the Earliest Fit
, the Latest Finis
, the Earliest Fi
7. What is the critical path? (please write down the letters only. For example, if y
ABCEFGH
8. Suppose you need to crash the project. The activity that will be crashed first is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!