Question: Question Completion Status: D G QUESTION 1 8 The following table of probabilistic time estimates ( in weeks ) and activity predecessors are provided for
Question Completion Status:
D
G
QUESTION
The following table of probabilistic time estimates in weeks and activity predecessors are provided for a project.
Activity
Immediate
Predecessor
Optimistic Time
Most Probable
Time
A
Pessimistie Time
D E
F
Table
Reference: Ref
Using Table the variance of the project's total completion time is approximately
O A
B
C
D
E None of the above
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
