- QUESTION COMPLETION STATUS Question 16 Academic Toolbox Grammar Check Tool Academic Referencing Tool CSU Library Library Study Support 1 points Learning Opportunities Useful Links The following represents a project with four activities. All times are in weeks. Activity Immediate Optimistic Most Likely Pessimistic Predecessor Time Time Time A 2 8 14. B 8 R c 6 19 18 D B 15 17 According to the table, what is the critical path? O a BD ODAB OCA-C Od. A-B-C-D