Question: Question Completion Status: Two possible routes for a power line are under study. In both cases the power line will last 15 years, have no
Question Completion Status: Two possible routes for a power line are under study. In both cases the power line will last 15 years, have no salvage value, and have a yearly power loss of $500/km. Around Under the Lake the Lake Length 12 km 4 km $26.000/km First Cost Maintenance $10,000km $300/km/year $600/km/year If 4% interest is used, choose the answer closest to the difference between the EUACs of the routes 1. 56600 2. $7100 3.$6800 4.57300