Question: Question content area Part 1 Development of Version 2 . 0 of a particular accounting software product is being considered by Jose Noguera's technology firm

Question content area
Part 1
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity
Normal Time(weeks)
Crash Time(weeks)
Normal Cost
Total Cost with Crashing
Immediate Predecessor(s)
A
44
33
$ 2 comma 000$2,000
$ 2 comma 650$2,650
long dash
B
22
11
$ 2 comma 300$2,300
$ 2 comma 900$2,900
long dash
C
33
33
$ 500$500
$ 500$500
long dash
D
88
44
$ 2 comma 300$2,300
$ 2 comma 580$2,580
A
E
66
33
$ 900$900
$ 1 comma 275$1,275
B
F
33
22
$ 3 comma 400$3,400
$ 4 comma 900$4,900
C
G
44
22
$ 1 comma 600$1,600
$ 2 comma 000$2,000
D, E
Part 2
a) Based on the given information regarding the activities for the project, the project length=
1616 weeks.
Part 3
b) The total cost required for completing this project on normal time=$
1300013000.
Part 4
c) For reducing the duration of the project by one week, the activity that should be crashed first is activity
D
.
Part 5
The cost of the project based on the first activity selected for crashing will increase by $
7070.
Part 6
d) The maximum weeks by which the project can be reduced by crashing=
7
weeks.
Part 7
Total cost of crashing the project to minimum(or maximum weeks possible)=$
1,4551,455.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!