Question: Question content area Part 1 Given the information below, estimate the probability that the noncritical path Upper B dash Upper F dash Upper G will
Question content area
Part
Given the information below, estimate the probability that the noncritical path Upper B dash Upper F dash Upper G will take more than weeks. Hint: Subtract from the probability that Upper B dash Upper F dash Upper G will take weeks or less. Refer to the standard normal tableLOADING....
Activity
Expected Time weeks
Variance
A
B
C
D
E
F
G
Part
The probability that this path will take more than weeks to compl
Given the information below, estimate the probability that the noncritical path BFG will take more than weeks. Hint: Subtract from the probability that BFG will take weeks or less. Refer to the standard normal table.
tableActivityExpected Time weeksVarianceABCDEFG
The probability that this path will take more than weeks to complete is Enter your response rounded to four decimal places.
The table below shows the total area under the normal curve for a point that is Z standard deviations to the right of the mean.
tableZtabletabletabletabletabletabletable