Question: Question content area Part 1 The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for
Question content area
Part
The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $ per day. The company will incur a $ per day penalty for each day the project lasts beyond day
Activity
Normal Timedays
Normal Cost$
Crash Timedays
Crash Cost
$
Immediate Predecessors
A
comma
minus
B
comma
comma
minus
C
A B
D
comma
comma
B
E
comma
comma
C D
F
comma
comma
E
G
E
H
G
Part
a What is the project's duration if only normal times are used?
The project duration is
enter your response here daysEnter your response as an integer.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock