Question: Question content area Part 1 The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for

Question content area
Part 1
The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $250 per day. The company will incur a $200 per day penalty for each day the project lasts beyond day 12.
Activity
Normal Time(days)
Normal Cost($)
Crash Time(days)
Crash Cost
($)
Immediate Predecessor(s)
A
5
800
4
1 comma 000
minus
B
5
1 comma 100
2
2 comma 900
minus
C
2
600
1
900
A, B
D
3
1 comma 200
2
2 comma 000
B
E
3
1 comma 500
2
1 comma 700
C, D
F
2
1 comma 300
1
1 comma 400
E
G
3
900
3
900
E
H
5
500
2
800
G
Part 2
a. What is the project's duration if only normal times are used?
The project duration is
enter your response here day(s).(Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!