Question: Question content area Part 1 When matching resources to customer demands, manufacturers strive to make schedules that achieve which of the following? Part 2 A
Question content area
Part
When matching resources to customer demands, manufacturers strive to make schedules that achieve which of the following?
Part
A
maximum workinprocess
B
low setup times
C
low facility utilization
D
short break times