Question: Question content area Part 1 When the latest start time is known, total slack for an activity may be determined using Part 2 A .

Question content area
Part 1
When the latest start time is known, total slack for an activity may be determined using
Part 2
A.
earliest start time.
B.
earliest finish time.
C.
latest finish time.
D.
activity time.