Question: Question content area Part 1 Yost - Perry Industries ( YPI ) manufactures a mix of affordable guitars ( A , B , C )

Question content area
Part 1
Yost-Perry Industries(YPI) manufactures a mix of affordable guitars(A, B, C) that are fabricated and assembled at four different processing stations(W, X, Y, Z). The operation is a batch process with small setup times that can be considered negligible. The product information(price, weekly demand, and processing times) and process sequences are shown below. Purchased parts and raw materials(shown as a per-unit consumption rate) are represented by inverted triangles. YPI is able to make and sell up to the limit of its demand per week with no penalties incurred for not meeting the full demand. Each workstation is staffed by one highly skilled worker who is dedicated to work on that workstation alone and is paid $15 per hour. The plant operates one8-hour shift per day and operates on a5-day work week(i.e.,40 hours of production per person per week). Overhead costs are $9,000/week.
$11
$8
$4
$5
Step 1
Step 1
Station W
Station W
Step 2
Step 2
Station Y
Station Z
Product A
Product B
Raw materials
Raw materials
(13 min)
(8 min)
(13 min)
(10 min)
Purchased part
Step 1
Product C
Step 2
Station X
Purchased part
Purchased part
Raw materials
Station W
$14
$5
(20 min)
(9 min)
In the diagram, a flowchart represents the manufacturing process of products A, B, and C in different rows. From top to bottom, rows are arranged for Product A, Product B, and Product C, respectively. Each row begins with an inverted triangle containing the dollar amount for the raw materials that go into the process. An arrow that emerges from the triangle is followed to the right by a series of rectangles for each step in the process. Each rectangle contains the step number, station name where that step takes place, and duration in minutes for that step. Between steps 2 and 3, each process has a purchased part added to the flow as indicated by an inverted triangle with the dollar amount for the purchased part inside. The final step in each process is followed by an arrow to a summary process that shows the product name, price per unit, and demand in units per week for that product. For product A, a value of $11 is displayed inside the initial triangle. For Step 1, Station W is used and the step takes 13 minutes. For Step 2, Station Z is used and the step takes 10 minutes. After step 2, a purchased part costing $5 is added to the flow. For Step 3, Station X is used and the step takes 9 minutes. The final output arrow points to summary process that reads Product: A, Price: $105 per unit, and Demand: 66 units per week. For product B, a value of $8 is displayed inside the initial triangle. For Step 1, Station W is used and the step takes 8 minutes. For Step 2, Station Y is used and the step takes 13 minutes. After step 2, a purchased part costing $4 is added to the flow. For Step 3, Station Z is used and the step takes 8 minutes. The final output arrow points to summary process that reads Product: B, Price: $95 per unit, and Demand: 80 units per week. For product C, a value of $14 is displayed inside the initial triangle. For Step 1, Station X is used and the step takes 9 minutes. For Step 2, Station W is used and the step takes 20 minutes. After step 2, a purchased part costing $5 is added to the flow. For Step 3, Station Y is used and the step takes 5 minutes. The final output arrow points to summary process that reads Product: C, Price: $110 per unit, and Demand: 66 units per week.
Step 3
Step 3
Station X
Station Z
Product: A
Product: B
(9 min)
(8 min)
Price: $105/unit
Demand: 66 units/wk
Demand: 80 units/wk
Price: $95/unit
Step 3
Station Y
(5 min)
Product: C
Price: $110/unit
Demand: 66 units/wk
x y graph
Part 2
Which of the four workstations, W, X, Y, or Z has the highest aggregate workload, and thus serves as the bottleneck for YPI?
Workstation W
Workstation X
Workstation Y
Workstation Z
, with a total load time of
enter your response here minutes. (Enter your response as an integer.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!