Question: Question Content Area The following data relate to direct labor costs for the current period: Standard costs 7,200 hours @ $11.10 Actual costs 6,300 hours
-
Question Content Area
The following data relate to direct labor costs for the current period:
Standard costs 7,200 hours @ $11.10 Actual costs 6,300 hours @ $10.80 What is the direct labor rate variance?
a.$11,880 unfavorable
b.$1,890 favorable
c.$11,880 favorable
d.$9,990 favorable