Question: Question content area top Part 1 The first step in developing an ABC system is Question content area bottom Part 1 A . calculate an

Question content area top
Part 1
The first step in developing an ABC system is
Question content area bottom
Part 1
A.
calculate an activity cost allocation rate for each activity.
B.
select an allocation base for each activity.
C.
allocate the costs to the cost object using the activity cost allocation rates.
D.
identify the primary activities and estimate a total cost pool for each.