Question: Question For a construction project, the project team has come up with the following set of activities with their durations and costs ( see Table

Question
For a construction project, the project team has come up with the following set of activities with their durations and costs (see Table below). For simplicity, the crash cost of the activities per day is assumed to be linear. The indirect cost is $48k per day.
\table[[Activity,IPA,\table[[Normal Duration],[(Days)]],\table[[Normal Direct],[Cost (k)]],\table[[Crash Duration],[(Days)]],\table[[Crash Direct],[Cost (k)]]],[A,-,7,140,6,210],[B,-,5,100,5,100],[C,A,3,90,2,140],[D,A,5,100,3,130],[E,A,5,60,4,100],[F,C,4,120,3,140],[G,D, F,6,180,4,240],[H,E,7,150,5,200],[J,B,2,40,2,40],[K,E, J,5,120,4,160],[L,G, H, K,4,80,4,80],[M,E, J,8,180,5,240]]
Using the information provided in the table, please:
a. Draw the Activity-On-Arrow (AOA) network diagram (30 marks)
b. Identify the critical path (or critical paths)(5 marks)
c. Calculate the total duration and the total cost of the project (5 marks)
d. Calculate the total float time of each non-critical activity (5 marks)
If the project team wants to shorten the project duration by two days, please:
a. For each day of shortening of the project, determine the activity (or activities) that would be the most appropriate to crash for the optimal cost effectiveness of the project; and re-calculate the total cost of the project after each day of shortening. (40 marks)
b. Draw the AOA network diagram after the two-day crash. (10 marks)
c. Identify the critical path (or critical paths) of the AOA network diagram after the two-day crash. (5 marks)For a construction project, the project team has come up with the following set of activities with their
durations and costs (see Table below). For simplicity, the crash cost of the activities per day is
assumed to be linear. The indirect cost is $48k per day.
Activity IPA Normal Duration
(Days)
Normal Direct
Cost (k)
Crash Duration
(Days)
Crash Direct
Cost (k)
A -71406210
B -51005100
C A 3902140
D A 51003130
E A 5604100
F C 41203140
G D, F 61804240
H E 71505200
J B 240240
K E, J 51204160
L G, H, K 480480
M E, J 81805240
1. Using the information provided in the table, please:
a. Draw the Activity-On-Arrow (AOA) network diagram (30 marks)
b. Identify the critical path (or critical paths)(5 marks)
c. Calculate the total duration and the total cost of the project (5 marks)
d. Calculate the total float time of each non-critical activity (5 marks)
Question For a construction project, the project

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!