Question: Question For a construction project, the project team has come up with the following set of activities with their durations and costs ( see Table
Question
For a construction project, the project team has come up with the following set of activities with their durations and costs see Table below For simplicity, the crash cost of the activities per day is assumed to be linear. The indirect cost is $ per day.
tableActivityIPA,tableNormal DurationDaystableNormal DirectCost ktableCrash DurationDaystableCrash DirectCost kABCADAEAFCGD FHEJBKE JLG H KME J
Using the information provided in the table, please:
a Draw the ActivityOnArrow AOA network diagram marks
b Identify the critical path or critical paths marks
c Calculate the total duration and the total cost of the project marks
d Calculate the total float time of each noncritical activity marks
If the project team wants to shorten the project duration by two days, please:
a For each day of shortening of the project, determine the activity or activities that would be the most appropriate to crash for the optimal cost effectiveness of the project; and recalculate the total cost of the project after each day of shortening. marks
b Draw the AOA network diagram after the twoday crash. marks
c Identify the critical path or critical paths of the AOA network diagram after the twoday crash. marksFor a construction project, the project team has come up with the following set of activities with their
durations and costs see Table below For simplicity, the crash cost of the activities per day is
assumed to be linear. The indirect cost is $k per day.
Activity IPA Normal Duration
Days
Normal Direct
Cost k
Crash Duration
Days
Crash Direct
Cost k
A
B
C A
D A
E A
F C
G D F
H E
J B
K E J
L G H K
M E J
Using the information provided in the table, please:
a Draw the ActivityOnArrow AOA network diagram marks
b Identify the critical path or critical paths marks
c Calculate the total duration and the total cost of the project marks
d Calculate the total float time of each noncritical activity marks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
