Question: QUESTION FOUR [20] Company A is attempting to predict future profit from a new project and the following probability distribution has been prepared: State 1
![QUESTION FOUR [20] Company A is attempting to predict future profit](https://s3.amazonaws.com/si.experts.images/answers/2024/07/66a5ed9ae9864_29866a5ed9a870aa.jpg)
QUESTION FOUR [20] Company A is attempting to predict future profit from a new project and the following probability distribution has been prepared: State 1 2 Probability 0.10 0.40 0.40 0.10 R23 000 Profit -R150 000 -R20 000 R40 000 R300 000 3 4 Expected value Required: Should the company accept the new project