Question: QUESTION FOUR [25] 4.1 The following table represents a project you are working on. Activity Predecessor Time (days) Optimistic Time (days) Most likely Time (days)

QUESTION FOUR [25]

4.1 The following table represents a project you are working on.

Activity

Predecessor

Time (days)

Optimistic

Time

(days)

Most likely

Time (days)

Pessimistic

t

v

a

-

15

18

25

b

-

15

18

20

c

a,b

6

10

12

d

c

18

24

26

e

d

13

19

25

f

d

12

18

23

g

d

15

17

19

h

f,g

22

25

30

i

e,f

11

15

17

4.2 Describe how the network diagram (AON) can be used for the information presented

above. (diagram not required)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!