Question: QUESTION FOUR 4.1 The following table represents a project you are working on. Activity Predecessor Time (days) Optimistic Time (days) Most likely Time (days) Pessimistic

QUESTION FOUR 4.1 The following table represents a project you are working on.

Activity

Predecessor

Time (days)

Optimistic

Time

(days)

Most likely

Time (days) Pessimistic

t

v

a

-

15

18

25

b

-

15

18

20

c

a,b

6

10

12

d

c

18

24

26

e

d

13

19

25

f

d

12

18

23

g

d

15

17

19

h

f,g

22

25

30

i

e,f

11

15

17

4.1 Calculate the time (t) and variance (v) for each activity. (8)

4.2 Describe how the network diagram (AON) can be used for the information presented above. (diagram not required) (12)

4.3 Identify the paths and the critical path. (5)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!