Question: Question: Given the following project network, baseline, and status information, fill in the blank status reports templates for periods 2, 4, 6, 8 included below
Question: Given the following project network, baseline, and status information, fill in the blank status reports templates for periods 2, 4, 6, 8 included below and complete the Performance Indexes Summary table. Based on your data, what is your assessment of the current status of the project?




LEGEND ES ID EF Budget (5000) 0 5 6 9 7 8 4 C8 2 2 6 4 10 10 11 12 SL SL 1 2 3 4 10 10 10 10 A 40 OA 4 LS OUR LF B 32 1 1 145 C 48 $D 10 0 0 5 5 10 10 F12 0 0 10 212 D 18 E 28 OB5 0 0 055 F 40 5 E8 Total 206 20 20 1814 18 14 20 26 22 26 2 6 20 20 32 50 64 84 110 132 158 160 166 186 206 2 2 7 3 10 Cumulative 18 (Sooo) B AC 25 12 37 (S000) AC 35 A 59 (5000) Status Report: Ending Period 2 Task * Complete 75% 5056 Cumulative Totals Status Report: Ending Portiod 4 Task % Completo 100% 100% Cumulativo Totals Status Report: Ending Period 6 Task * Completo 100% 100% 75% Ox so Cumulativo Totals Status Report: Endling Period 8 Task * Completo 100% 100% 100% D 100% Cumulative Totals 93 (SOOO) A B Performance Indieses Summary Period EV 2 AC SPI CPI PCIB 6 Please complete the Status Report (fill in the table) as of Period 2. End of Period 2 Actual % EV AC PV CV SV Task Complete $ $ $ $ $ $ 75 B 50 0 D 0 E 0 Cumulative Totals End of Period 6 Actual % EV AC PV CV SV Task Complete $ $ $ $ $ B C D E Cumulative Totals Please complete the Status Report (fill in the table) as of Period 8. End of Period 8 Actual % EV AC PV CV SV Task Complete $ $ $ $ $ B D E Please complete the Performance Indexes Summary (fill in the table below). Performance Indexes Summary Period EV AC PV SPI CPI PCIB 2 4 6 8 Based on your data, what is your assessment of the current status of the project? Response should discuss the status in terms of cost and schedule. Reference the data in the tables above. Suggested response length is 1-2 paragraphs