Question: Question: In construction management, what does the term critical path refer to ? A ) The shortest route for materials delivery B ) The longest

Question:
In construction management, what does the term "critical path" refer to?
A) The shortest route for materials delivery
B) The longest sequence of activities determining the shortest possible project duration
C) The designated path for emergency evacuation
D) The primary access route for construction vehicles