Question: Question: In the context of project scheduling, what does PERT stand for? A ) Program Evaluation and Review Technique B ) Project Execution and Resource

Question: In the context of project scheduling, what does "PERT" stand for?
A) Program Evaluation and Review Technique
B) Project Execution and Resource Tracking
C) Performance Evaluation and Reporting Tool
D) Project Efficiency and Resource Time
if itss wrong i will give downvote

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!