Question: Question list The demand for subassembly S is 8 0 units in week 7 . Each unit of S requires 2 units of T and

Question list
The demand for subassembly S is 80 units in week 7. Each unit of S requires 2 units of T and 1 unit of U. Each unit of T requires 1 unit of V,1 unit of W, and 2 units of x. Finally, each unit of U requires 1 unit of Y and 2 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W,1 week to make x,2 weeks to make Y, and 1 week to make Z.
Question 1
Question 2
Question 3
Question 4
Question 5
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Suppose that in addition to 80 units of S, there is also a demand for 30 units of U, which is a component of S. The 30 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 70 units of S due in week 8. Modify the net material requirements plan to reflect these changes.
Construct a new net material requirements plan (enter your responses as whole numbers).
\table[[Item,Week,\table[[Lead Time],[(weeks)]]],[,,1,2,3,4,5,6,7,8],[s,Gross req,,,,,,,,,2],[On hand,,,,,,,,],[Net req,,,,,,,,],[Order receipt,,,,,,,,],[Order release,,,,,,,,]]
More Info
The product structure.
Level
0
The time-phased product structurla
More Info
\table[[Item,\table[[On-Hand],[Inventory]],Item,\table[[On-Hand],[Inventory]]],[S,20,W,30],[T,20,x,30],[U,30,Y,30],[V,20,Z,40]]
 Question list The demand for subassembly S is 80 units in

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!