Question: Question No. 03. [08 Marks] A Hospital Management System Development Project has a budgeted cost of Rs. 11,900,000/-. The project is to be completed in
Question No. 03. [08 Marks]
A Hospital Management System Development Project has a budgeted cost of Rs. 11,900,000/-. The project is to be completed in 11 months. After 4 months, you have completed 24 percent of the project at a total expense of Rs. 1,475,000/-. You, as a Project Manager, needs to submit the monthly performance report to the Steering Committee. Based on EVM methodology, please identify the current progress of the Project.
- Find Budget at Completion (BAC), Actual Cost(AC), Planned Value (PV) and Earned Value (EV).
- Calculate the Project Health by finding values of Schedule Variance (SV), Schedule Performance Index (SPI), Cost Variance (CV) and Cost Performance Index (CPI). What these value shows?
- If the project continues at the current pace, what will be the true cost of the Project or Estimate at completion of the project.
- What actions, You would suggest or take as a Project Manager, to keep the budget and time under control.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
