Question No. 05 [06 Marks] Part 5A: A project with Earned Value (EV) = Rs. 1600, Actual Cost (AC) = Rs. 800 and Schedule performance Index (SPI) = Rs 200. What is the Schedule Variance (SV)? Part 5B: A project with Earned Value (EV)= Rs 1000, Cost Schedule performance Index (CPI) = Rs 200 and Planned Value (PV) = Rs 800. What is the Cost Variance (CV)