Question: Question No. 2: The table represent project scheduling: Complete this table to determint the critical path for the project. EFT LST LFT SLACK On critical

Question No. 2: The table represent project
Question No. 2: The table represent project scheduling: Complete this table to determint the critical path for the project. EFT LST LFT SLACK On critical path? Yes or No 4 7 Activity Activity EST Time A 4 0 B 3 2 4 D 5 E 3 7 F 4 12 G 3 16 0 4 10 12 10 9 12 12 12 16 19 DONNIN