Question: Question No. 22 In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting

Question No. 22 In the time-cost optimisation, using CPM method for network analysis, the crashing of the activities along the critical path is done starting with the activity having (A) Longest duration (B) Highest cost slope (C) Least cost slope (D) Shortest duration