Question: QUESTION NO . 9 Two loads, A and B , are connected in parallel across a 1 - KV rms 6 0 HZ line as

QUESTION NO.9
Two loads, A and B , are connected in parallel across a 1-KV rms 60 HZ line as shown in the following. Load A consumes 5 KW with a \(90\%\) lagging power factor. Load B consumes 10 KW with an 80 percent leading power factor.
Test 3- Part B
Find the apparent power delivered by the source?
A.15.64 KVA
B.15.74 KVA
C.15.84 KVA
D.15.94 KVA
E. No correct answer