Question: question number 9 A manager needs to decide whether or not to hire one more hour of labor. The MPL is 40 units, the selling

question number 9

question number 9 A manager needs to decide whether or not to

A manager needs to decide whether or not to hire one more hour of labor. The MPL is 40 units, the selling price of the output is $0.75 per unit, and the hourly wage is $32.00. Which of the following indicates what the manager should do and for the right reason? O The manager should hire the additional hour of labor because the VMPL is positive. O The manager should hire the additional hour of labor because the VMPL is greater than the wage rate. O The manager should not hire the additional hour of labor because the wage rate is greater than the per-unit price. O The manager should hire the additional hour of labor because the MPL is positive. The manager should not hire the additional hour of labor because the VMPL is less than the wage rate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Economics Questions!