Question: QUESTION: perform the CPM computations to determine (i) early and late start and finish dates for all activities, (ii) free floats and total floats for
QUESTION: perform the CPM computations to determine (i) early and late start and finish dates for all activities, (ii) free floats and total floats for all activities (iii) critical activities and (iv) critical path.
Draw CPM activity diagram and Summary Table.
FOR BOTH CASES
CASE 1:
| Activity | Duration | Predecessor | Lag |
| A | 5 | - | |
| B | 6 | A | |
| C | 4 | A | 3 |
| D | 5 | A | |
| E | 9 | B | |
| F | 7 | B | 2 |
| C | |||
| G | 6 | C | |
| H | 8 | C | |
| D | 4 | ||
| I | 3 | D | |
| J | 7 | E, G | |
| F | 2 | ||
| K | 4 | F, G, H | |
| L | 1 | H | 3 |
| I | |||
| M | 2 | K, L |
CASE 2: (show each and every possiblitiy on CPM activity diagram)
| Activity | Duration | Predecessor |
| A | 20 | - |
| B | 10 | A (SS5, FF6) |
| C | 10 | A |
| D | 17 | A (SS7, FF3) |
| E | 15 | B (SS7, FF0) |
| F | 8 | C (FS5) |
| G | 4 | C (SS1, FF1) |
| H | 6 | D (SS10, FF2) |
| I | 5 | E (SS2, FF2), F (FS10) |
| J | 9 | G |
| K | 12 | G, H |
| L | 12 | I, J, K (SS3, FF7) |
Thanks in advance.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
