Question: QUESTION: perform the CPM computations to determine (i) early and late start and finish dates for all activities, (ii) free floats and total floats for

QUESTION: perform the CPM computations to determine (i) early and late start and finish dates for all activities, (ii) free floats and total floats for all activities (iii) critical activities and (iv) critical path.

Draw CPM activity diagram and Summary Table.

FOR BOTH CASES

CASE 1:

Activity Duration Predecessor Lag
A 5 -
B 6 A
C 4 A 3
D 5 A
E 9 B
F 7 B 2
C
G 6 C
H 8 C
D 4
I 3 D
J 7 E, G
F 2
K 4 F, G, H
L 1 H 3
I
M 2 K, L

CASE 2: (show each and every possiblitiy on CPM activity diagram)

Activity Duration Predecessor
A 20 -
B 10 A (SS5, FF6)
C 10 A
D 17 A (SS7, FF3)
E 15 B (SS7, FF0)
F 8 C (FS5)
G 4 C (SS1, FF1)
H 6 D (SS10, FF2)
I 5 E (SS2, FF2), F (FS10)
J 9 G
K 12 G, H
L 12 I, J, K (SS3, FF7)

Thanks in advance.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!