Question: Question six a) Define a project budget b) Differentiate between planned value and actual value c) A 12-month project is in its 6th month (50%
Question six
a) Define a project budget
b) Differentiate between planned value and actual value c) A 12-month project is in its 6th month (50% of the time has been used), but has accomplished only 40% of its activities and has spent 60% of its financial resources according to the latest financial report. The total budget for the projects is $2,400,000.
Calculate
i) Planned value
ii) Actual cost
iii) Earned value
iv) Cost variance
v) Schedule variance
vi) Cost performance index
vii)Schedule performance index
How can a project manager know if his project is on track or not?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
