Question: Question: Task Name Duration Predecessors National Stadium Lighting (NSL) Project Study CSC requirements 5 days Design LED by BSA 10 days 2 Design power requirements
Question:
| Task Name | Duration | Predecessors |
| National Stadium Lighting (NSL) Project | ||
| Study CSC requirements | 5 days | |
| Design LED by BSA | 10 days | 2 |
| Design power requirements | 3 days | 2 |
| Manufacture LED | 11 days | 3 |
| Design light controlling software | 8 days | 2 |
| Deliver LED | 9 days | 5 |
| Install new power supply | 7 days | 4 |
| Install controlling computer | 6 days | 6 |
| Lay network cables | 5 days | 9 |
| Lay power cables | 4 days | 8 |
| Install LED | 6 days | 7,10,11 |
| Test LED System | 3 days | 12 |
| Certifcation by Building & Construction Authority (BCA) | 7 days | 13 |
| Commision NSL System | 1 day | 14 |
b) Analyse five (5) potential risks that may happen in the NSL Project, one from each of the categories: Technical, External, Organisational, Project Management and Customer.
| Item | Category | Description of Risk | Consequence |
| Risk 1 | Technical | ||
| Risk 2 | External | ||
| Risk 3 | Organisational | ||
| Risk 4 | Project Management | ||
| Risk 5 | Customer |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock