Question: The ACME rodenticide company has the following projected requirements for packs of its rat poison: Week
Fantastic news! We've Found the answer you've been seeking!
Question:
Question: The ACME rodenticide company has the following projected requirements for packs of its rat poison:
Week June 1: 2350
Week June 8: 2460
Week June 15: 1590
Week June 22: 2789
Week June 29: 1962
Week July 6: 1757
Before June 1, a stocktake shows that there are 3367 units in stock.
The following production rules apply:
There is a one week production lead-time
The batch size is 250 units
There is a safety stock requirement of 500units
You should product the minimum amount in any week to meet requirements and not breech the safety stock requirements