Question: Question: The team plans each sprint and captures the tasks in the Sprint Backlog. This activity is time - boxed and should take no more

Question: The team plans each sprint and captures the tasks in the Sprint Backlog. This activity is time-boxed and should take no more than:2 hours6 hours4 hours1 dayThe team plans each sprint and captures the tasks in the Sprint Backlog. This activity is time-boxed and should take no more than:2 hours6 hours4 hours