Question: QUESTION THREE [ 2 0 ] You are planning a party with a budget of R 5 0 0 . After of week of planning,

QUESTION THREE [20] You are planning a party with a budget of R500. After of week of planning, youve undertaken tasks worth R200. However you spent R150. Calculate the following: 3.1 Earned value (EV)(4)3.2 Schedule variance (SV)(4)3.3 Cost variance (CV)(4)3.4 Schedule performance index (SPI)(4)6.5 Cost performance index (CPI)(4)