Question: QUESTION TWO (Homework) Consider a project which has been modeled as follows: 10 Activity Immediate Predecessor (8) Completion Time (hours) A 7 B A 4

 QUESTION TWO (Homework) Consider a project which has been modeled as

QUESTION TWO (Homework) Consider a project which has been modeled as follows: 10 Activity Immediate Predecessor (8) Completion Time (hours) A 7 B A 4 D A 30 E A 7 F BC 12 G B.C 15 H EF 11 I E.F 25 J E.F 6 K DH L GJ Required: Determine the project's expected completion time and its critical path. 21 25