Question: QUESTION TWO (Homework) Consider a project which has been modeled as follows: 10 Activity Immediate Predecessor (8) Completion Time (hours) A 7 B A 4
QUESTION TWO (Homework) Consider a project which has been modeled as follows: 10 Activity Immediate Predecessor (8) Completion Time (hours) A 7 B A 4 D A 30 E A 7 F BC 12 G B.C 15 H EF 11 I E.F 25 J E.F 6 K DH L GJ Required: Determine the project's expected completion time and its critical path. 21 25
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts