Question: Question : Which metric quantifies the delta between estimated resource cost and actual resource cost? Instruction: Choose the option that best answers the question. Planned
Question
:
Which metric quantifies the delta between estimated resource cost and actual resource cost?
Instruction:Choose the option that best answers the question.
Planned Resource Utilization
Usage Variance
Price Variance
Resource Allocation Ratio