Question: Question Z (2 points) () Listen Four new risks for a project are identified while the project manager is preparing the monthly project status report.

 Question Z (2 points) () Listen Four new risks for a

Question Z (2 points) () Listen Four new risks for a project are identified while the project manager is preparing the monthly project status report. These four risks could affect vital key milestones. What should the project manager do before presenting this new risk information? Select one. Review the risk report and lessons learned repository. Refer to the risk management plan and the risk report. Refer to the risk register as well as the risk report. Review the organizational process assets and risk register