Question: Questions 1 8 4 - 1 8 9 are based on the following information: Estimate: 1 9 5 0 units of material Crew size -
Questions are based on the following information:
Estimate:
units of material
Crew size workers
Total duration weeks
Workers work hrs per day days a week
After weeks:
units of material placed
crew hours expended
$ labor spent
What is the actual crew productivity rate in units per hour?
a
b
c
d