Question: Questions 1 . Draw an Activity - on - Node Diagram for the following: Activity Name Predecessor ( s ) A None B none C

Questions
1. Draw an Activity-on-Node Diagram for the following:
Activity Name Predecessor(s)
A None
B none
C A
D A,B
E D
F C
G F,E
H G
3. Using the PERT (Program Evaluation Review Technique) estimating method, calculate the expected time (TE) for each of the following activities.
Activity Optimistic (days) Pessimistic (days) Most Likely (days)
Activity A 2124
Activity B 52520
Activity C 105018
Activity D 3107