Question: Questions 1 . Draw an Activity - on - Node Diagram for the following: Activity Name Predecessor ( s ) A None B none C
Questions
Draw an ActivityonNode Diagram for the following:
Activity Name Predecessors
A None
B none
C A
D AB
E D
F C
G FE
H G
Using the PERT Program Evaluation Review Technique estimating method, calculate the expected time TE for each of the following activities.
Activity Optimistic days Pessimistic days Most Likely days
Activity A
Activity B
Activity C
Activity D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
