Question: Questions 2 : [ 3 0 ] You are a project manager overseeing the construction of a new office building. The project involves several activities,

Questions 2:
[30]
You are a project manager overseeing the construction of a new office building. The project involves several activities, each with a specific duration and set of dependencies. The goal is to complete the project in the shortest possible time. Below is the list of activities with their durations and dependencies:
\table[[Activity,Duration (days),Predecessors],[A,5,None],[B,3,A],[C,8,A],[D,6,B],[E,4,B, C],[F,2,C],[G,7,D, E],[H,3,E],[I,5,F, H],[J,6,H, I]]
2.1. Construct a network diagram.
(7)
2.2. Determine ES, EF, LS, LF, Slack.
(17)
2.3. Determine the critical path and project completion time.
(3)
2.4. If you need to reduce the project duration by 4 days, identify which activities should be expedited (crashed) and how many days each should be reduced.
(3)
 Questions 2: [30] You are a project manager overseeing the construction

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!