Question: Questions 2 activity arrow - diagram is missing question 1 ) you missed th C Activity has A is the predecssors. you did with no
Questions activity arrowdiagram is missing
question you missed th C Activity has A is the predecssors. you did with no predecsseros.
question you missed F Activity has CD predecssors. you did only D
please do it again and I need the Digram too
Draw an ActivityonNode Diagram, identify project duration and project critical path for the following:
Activity name Predecessors Durationweek
A None
B none
C A
D AB
E D
F E
Draw an ActivityonArrow Diagram, identify project duration, slack for each activity, and project critical path for the following:
Activity name Predecessors Durationweek
A none
B none
C none
D AB
E C
F CD
G EF
Draw an ActivityonNode Diagram, identify activity duration, slack for each activity,project duration, and project critical path for the following:
Activity name Predecessors a m b
A none
B none
C none
D A
E BC
F CD
G F
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock