Question: Questions: Figure 3 . 2 2 Soil profile for Problem 3 . 1 8 . ( 1 ) Compute the total ultimate settlement caused by
Questions:
Figure Soil profile for
Problem
Compute the total ultimate settlement caused by primary consolidation of the upper clay layer that is
"Medium Clay"
Consider CV of upper clay is mmmin Find the time at which onehalf of the primary consolidation
settlement of the upper clay layer will be completed. assume twoway drainage for upper clay
For this homework, we only estimate day consolidation settlement for upper Medium Clay.