Question: quickly pls 7. The table given below are actually the job orders received by Metal Fabrication Shop which specializes in customized metal parts. The table

quickly pls
 quickly pls 7. The table given below are actually the job

7. The table given below are actually the job orders received by Metal Fabrication Shop which specializes in customized metal parts. The table shows the processing time and due dates that are required per iob. 7.1. What is the job sequence using Johnson's Rule? ( 2 pts) a. D_C_A B b. B_D_C_A c. A-B-D-C 7.2. Considering the data in Q2, what will be the ECT time in WC 1 using EDD? ( 5 pts) a. 9 b. 10 c. 7 d. None of the above