Question: R 4 - 5 ( Static ) When would it be appropriate to create... When would it be appropriate to create a responsibility matrix rather
RStatic When would it be appropriate to create...
When would it be appropriate to create a responsibility matrix rather than a WBSYou may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer. Any boxes left with a question mark will be automatically graded as incorrect.
check all that apply
On a small project
On a complex project
On a multiyear project
On a project where face to face communication is impossible
On a segment of a larger project