Question: R 9 - 6 Reducing project duration... Reducing project duration can have other impacts besides Just time. These include: ( You may select more than

R9-6 Reducing project duration...
Reducing project duration can have other impacts besides Just time. These include: (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
May cause overallocation on some resources.
Reduces flexibility by using slack.
Can decrease interdependencies of paths.
May increase risk that project will be late.
Can increase number of critical activities.
May increase costs.
 R9-6 Reducing project duration... Reducing project duration can have other impacts

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!