Why is scheduling overtime a popular choice for getting projects back on schedule?

  • If it involves salaried workers, no direct costs are added to the project.unanswered
  • If it involves hourly workers no direct costs are added to the project.unanswered
  • Even if it involves additional costs, you minimize additional coordination and training costs.unanswered
  • It tends to avoid accidents, inferior performance, and turnover.

Step by Step Solution

There are 3 Steps involved in it